RECEIVING DFA’s

 

  1. Description:
  2. Receiving DFA's involves the following steps:

  3. Steps:

IMMEDIATELY UPON RECEIVING:

Rails: Use 4-40 x 1/4 Socket Head Cap Screws (SCHS)

Plastic Covers: 6-32 x 3/16 Button Head Cap Screws (BHCS)

Black Delron Clamps: 6-32 x 1/4 BHCS that have flat tops

Make sure these clamps are very clean! They hold the DFA in the ringframe, and the clamps sit directly on the wafers!

G-10: 6-32 x 1/4 SHCS;1/8" dowel pins which hold the G-10 in

the ringframe and 2 mm dowel pins in the G-10 used to position the upilex.

VISUAL INSPECTION:

ENTER PISA DATA INTO THE BONDMAP DATABASE:

3. People to ask if problems arise: